by staceyamcneill | Jun 21, 2018 | Victory Station
Today was tilt-up day for Victory Station. Well, the first tilt-up day. With 117 panels to tilt, this will take more than one day. We’re estimating the Devcon Construction team can tilt 25 panels a day, so we’re looking at five tilt-up days if all goes as planned. Why...
by staceyamcneill | Jun 18, 2018 | Victory Station
The Devcon Construction team has been hard at work preparing the 117 concrete panels for tilting this week. Once the panels solidify and the forms are removed, the crew attaches braces to the each tilt-up panel. They will connect each panel to a large crane with...
by staceyamcneill | Jun 8, 2018 | Victory Station
The temporary post currently supporting the flag at the Sonoma industrial building site was erected primarily to mount the time-lapse construction camera. The camera, operated by iBEAM Construction Cameras, snaps an image every 10 minutes. Images may be viewed from...